The status line markers help you track how task progress has evolved over time. Select the desired status line markers of specific dates to visually compare task performance. Each selected marker adds a stripe of same color of it to the task bars in the Gantt chart. Click the point where a colored bar intersects the date line of the same color to open a detailed task status card for that day. The card can be moved, pinned, and kept open while you continue reviewing other tasks.
- Status lines can be viewed only in the Gantt view or the Grid & Gantt split view of the schedule.
- Compare the current task status with any previously marked date to identify task progress.
- Compare multiple status lines to analyze trends and performance across key project milestones.
- Select up to three status lines for side-by-side comparison to gain clear insights into progress shifts.
Use the links below to jump to the section you need help with:
- Select Status Line Markers and Compare Tasks Statuses
- Delete Status Line Markers
- Change color of an existing status line marker
Select Status Line Markers and Compare Tasks Statuses
- Ensure that you are in the Gantt view or Grid and Gantt view of the 'Schedule' module. If not,
- Ensure that you are on the management console of the project
- Click the app launcher icon
in the top-right and select 'Schedule'
- Click 'Grid' on the left and select 'Grid and Gantt' from the drop down at the top, or
- Click 'Gantt' on the left
- Choose the dates for which you want to view the status line, from the 'Select Status Line' drop down
Note: You can select upto 3 status line marker and pin upto 3 tasks at a time for comparison.
Each selected marker overlays a horizontal stripe in its designated color across all task bars in the Gantt chart.
- Click where a colored task bar intersects with the status line of the same color to view the task’s progress on that specific date.
- Use the pin icon on the progress pop-up to keep it visible, and drag it to any position on the screen as needed for easier viewing.
- Repeat the process to see the progress of the same task with different status line marker to compare the progress at different instant
Delete Status Line Markers
- Open the project scheduler as mentioned above
- Click 'Grid' on the left and select 'Grid and Gantt' from the drop down at the top, or
- Click 'Gantt' on the left
- Expand the 'Status Line' drop down to view the list of status lines created for the project
- Click the 'Delete' icon near the status line date to delete the marker
- Click 'OK' to confirm your action
Change color of an existing status line marker
- Open the project scheduler as mentioned above
- Click 'Grid' on the left and select 'Grid and Gantt' from the drop down at the top, or
- Click 'Gantt' on the left
- Expand the 'Status Line' drop down to view the list of status lines created for the project
- Click on the color dot near the desired status line date
There are two ways in which you can specify color code:
- Color picker
- Drag the slider in the color spectrum bar to select the hue
- Drag the circle in the color field to select the shade
- Drag the slider in the opacity bar to set the color transparency level
- The color coordinates of the chosen color is auto-populated in the text box at the bottom
- Color coordinates
- Click the arrows at the bottom right repeatedly to switch between HEX, RGBA, and HSLA input modes
- Enter the HEX, RGBA, or HSLA value of the color you want to assign to the item
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article