Update Task Progress

Modified on Thu, 19 Feb at 1:37 AM

The cloud-based scheduler keeps track of the actual start date and progress of the task and dynamically updates the progress statistics on various dashboards and reports throughout the project management console.

Subcontractors

Typically, the contractor scheduler fetches the actual start date and daily progress updates of the field-level tasks from the field as input by the foreman. The contractor scheduler dynamically calculates the parent-level tasks' progress from the progress percentages of the field-level child tasks. The subcontractor project managers can also manually update the progress of tasks if required. Periodically, the SC PM shares the progress of the assigned task items with the GC. See Share task progress for more details.

General Contractors

Items assigned to the Subcontractors - The master schedule receives the task progress updates for the items as and when shared by the subs and notifies the GC PM. The GC PM should accept the progress updates to take effect on their schedule.

Items self-assigned to the GC - The GC can update the progress themselves, as explained here.

Note:  
  • The general contractor cannot update the tasks assigned to subcontractors directly.They can only receive the task progress updates shared by the respective subcontractors.

Actual Start Date from the Field - To ensure the Master Schedule reflects real-time site activity without manual intervention, actual start dates are derived directly from the field. Whether a work item is self-performed or assigned to a subcontractor, the moment a foreman logs progress on a leaf-level task, that initial start date automatically rolls up the WBS hierarchy to update the assigned root work item. 

To record the progress reported by a sub

  • Navigate to your 'Master Schedule' screen. 
    • Click the app launcher icon in the top-right  and select 'Schedule'
    • Click 'Planner' on the top, then select 'Grid' on the left to open the master schedule of the project

A 'Sync' icon appears in the progress column of the items for which the subcontractors have reported their progress.

  • Click the icon.

A confirmation appears with the details entered by the subcontractor:

  • Click 'Proceed' to add the progress details to your schedule

The progress percentage is added to the 'Progress' column of the item. The progress percentages of the items in the upper levels of the hierarchy are updated appropriately.

General contractors can enter their progress for the tasks assigned to their own company as self-performed work. The process is similar to that for subcontractors, as explained here.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article