View Estimate Allocation Log

Modified on Thu, 10 Jul at 5:49 AM

The 'Allocation Log' screen under estimates provides a detailed view of estimate allocations to the schedule tasks.

To view the linked budget items and allotted funds

  • Ensure that you're in the Project Estimates screen. If not:
    • Click the app launcherand select 'Finance' from the project management console
    • Click 'Estimates' on top

  • Select 'Allocation Log' from the left
Search and filter options:
  • Use the 'Search' box located at the top left to find any project using any value from the table as search criteria 
  • Right-click the column header and customize the display and order of the columns as you wish 
  • The options at the top right allow you to filter the entries, and manage personalized and customized views of the table. Use the links below to learn more about these:

View Groups and Subtotals

  • You can get totals and subtotals of numerical data for any selected set of records by grouping and applying nested grouping. Use the  icon at the top right to organize the data by column headers.
  • The system automatically aggregates relevant numerical values, giving a structured breakdown and a clear view of the grand total distribution. See Group and Organize Items in a List View for more details

Download as Excel Sheet

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article