After entering the estimated cost amounts for all line items across various cost types and saving the estimate, you can lock and publish it. Locking the estimate sets it as a fixed reference point for future comparisons and analysis. From the locked estimate, you can link costs to specific tasks, activities, or deliverables in the project’s schedule. Once an estimate is locked, it becomes read-only and cannot be changed, ensuring the data remains intact for auditing and accountability. You cannot:
Modify the original estimate values
Add sub line items
Delete any estimate line items
Any adjustments to the locked estimate must be handled through change orders.
To lock an estimate
- Ensure that you are in the Estimate Upload screen. if it is not already opened:
- Click the app launcher
and select 'Finance.'
- Click 'Estimate' at the top and 'Estimates' on the left
- Click the app launcher
Search and filter options:
- Use the 'Search' box located at the top left to find any project using any value from the table as search criteria
- Right-click the column header and customize the display and order of the columns as you wish
- The options at the top right allow you to filter the entries, and manage personalized and customized views of the table. Use the links below to learn more about these:
View Groups and Subtotals
- You can get totals and subtotals of numerical data for any selected set of records by grouping and applying nested grouping. Use the
icon at the top right to organize the data by column headers.
- The system automatically aggregates relevant numerical values, giving a structured breakdown and a clear view of the grand total distribution. See Group and Organize Items in a List View for more details
Download as Excel Sheet
- Click the
button at the top right to save a local copy of the list in Excel format for sharing and record-keeping. See Download List Views and Logs in Excel Format for more details.
- Review the project estimate and ensure it exhaustively covers all planned work
- Click 'Lock Estimates' on the top right
Note: The 'Lock Estimates' button appears only for saved estimates. If you haven't done so, click 'Save' to save the estimate file.
- Click 'Yes' in the confirmation dialog.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article