Request Work Cost Estimates from Subcontractors and Vendors

Modified on Wed, 11 Dec at 12:15 AM

Project managers can invite subcontractors/vendors to submit their work and cost estimates for contract change orders. Once the invitation is sent, the subcontractor is notified to accept the tender and submit their work cost estimates for the part of the work they perform as per the change order. Once the subcontractors/vendors submit their quotations, the GC can peruse, process, and finalize the change order.

Roles and Permissions:
Only users assigned with roles having 'Manage' permission or 'Invite' permission for Change order Invite(Bids) in the change order module can request bids from subcontractors and vendors.

The 'Work Estimate' screen of a change order screen enables you to request work cost estimates from the subcontractors/vendors and process their submitted estimates. This article explains how the general contractor can solicit bids from the subs and vendors. For detailed instructions on reviewing, processing, and approving submitted estimates, see the Process Change Order Bids page. 

To invite work estimates for a change order

  • Open the change order if not open already. To do so:
    • Ensure that you are on the project's management console
    • Click the app launcherand select 'Finance.' and click 'Change Order' on the top
    • Select 'Boards' on the left.
    • Click the change order card from the 'Drafts' column
    • If you have already submitted an estimate, the card will be available in the 'Bids in Process' column
  • Click the 'Work Estimate' tab
  • Click 'Request Bids' at the top right

  • The 'Select Companies' dialog shows the list of subcontractors, vendors, and other companies collaborating on the project.

  • Select the companies you want to invite the estimates from
Tip:
You can set the due dates for estimate submission to each invitee individually after setting-up the invites.
  • Click 'Continue' 

The confirmation dialog shows the list of selected companies:

  • Click 'Continue' 

  • Due Date - Click inside the 'Estimate Due Date' cell for each company and use the calendar to set up the bid submission due date for that company. 
  • The invitations are sent. The status column indicates the bid submission status of each invitee. Possible values are:

    • Invited - The bid request has been sent to the subcontractor.
    • Pending - The subcontractor has accepted the request and is yet to submit their bid.
    • Estimate Submitted - The subcontractor has submitted the bid. You can view/review these bids.
    • Estimate Revision - You have returned the bid for the subcontractor to submit a revised bid 
    • Estimate Accepted - The estimate submitted by the contractor has been processed and accepted.
    • Bid Cancelled - The estimate submitted by the contractor was rejected by the GC.
  • Once the invitees accept the bid request and submit their quotations, they will appear here. The 'Cost Impact' and 'Schedule Impact' values are auto-fetched from the estimate and shown here for your quick look. You can review, compare, and select the qualifying bids. You will get notified of every bid submission.

    Tip:
    You can chat with the team members and the participants of the change order at any stage. Click the button on the top right. See Chat and collaborate on a CO for more guidance.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article