The SOV module closely monitors task progress updates and maintains a dynamic list of SOV items available for claims in the current month's cycle. By leveraging progress data and allocated cost estimates for each task, it computes critical financial parameters such as cost values tied to the month's progress, profit margins, and other key metrics, ensuring precision in project financial management.

  • Progress Tracking: The 'My Progress' screen displays a list of items eligible for the current month's SOV, including progress and cost details sourced from contractor-maintained estimates.
  • Monthly Submission: Contractors can select items from the 'My Progress' screen and submit their SOVs during the submission window set by the general contractor (GC).
  • Review and Approval: Once SOV items are submitted, the GC reviews them thoroughly, either approving or revising as necessary. Approved SOVs enable the seamless generation of invoices for the billing period. If the project owner holds final approval authority, the GC forwards the reviewed SOVs to the owner for final validation and approval.
  • Self-Performed Tasks: GCs can also manage and approve SOVs for tasks performed in-house.

To view the available SOV items for the current cycle

  • Open the SOV' > 'My Progress' screen. To do so:
    • Ensure that you are on the management console of the project
    • Click the app launcher on the top-right and select 'Finance'
    • Click 'SOV' on the top, then select 'My Progress' from the options on the left

The table shows the list of SOV items that are eligible for invoicing with their details. All monetary values are calculated from the project estimates maintained by the contractor.

  • Task Code - The cost code for the task item as in the contractor schedule. 
  • Task Name - The label of the task item as in the contractor's schedule.
  • Shared Progress Date - The date on which the completion percentage was last reported to the GC by the contractor 
  • Scheduled Values (A) - The planned overall cost of the task.
  • Profit % (T) - The percentage of profit included in the total planned cost of the task. 
  • Work Completed: 
    • Till Last Period Amount (B) - The total of the billable amounts incurred for the task up to the previous billing date.
    • Till Last Period % (C) - The percentage of the 'Last Period Amount' for the task till last month relative to the planned overall cost of the task (Scheduled Value (A))
    • Current Period Amount (D) - The gross billable amount incurred for the task in the current billing period.
    • Current Period% (E) - The progress percentage of the task realized only in this month
  • Progress to Date (M) - The total completion percentage of the task reported till the current SOV submission date
  • Profit to Date (P) - The total profit accumulated till the current SOV
  • Current Retainage - The amount retained from the gross billable amount for the current billing period, as per the agreed SOV terms.
  • Net SOV (N) - The amount billable for the current billing period, excluding the retainage, in USD. ('This Period' (D) - 'Retainage' (R))
  •  Value To Date (G) - The gross total billable amount incurred for the task up to the current billing date, including retainage ('Last Period (B)' + 'This Period (D)' + 'Profit to date (P)')
  • Last Retainage -  The total value of the amounts withheld from previous billing cycles. 
  • Balance to Finish - The remaining amount in the task's total planned cost, after the current billing cycle. ('Scheduled Value (A)' - 'Value to Date (G)')

Search and filter options:

You can select the items you want to submit for this billing cycle by clicking the checkboxes in the 'S.No' column and clicking the 'Move to Open' button at the top right. See the next section, 'Submit your SOV for approval' for more details.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article