View and compare baselines
  • 1 Minute to read

    View and compare baselines


      Article Summary

      The baselines screen shows the list of baselines you created at various points in time along the course of the project. You can also have a granular comparison between selected baselines to analyze the successive revisions on timelines of affected tasks and your project's performance.

      View baselines

      • Open the project management console
      • Click 'Schedule' on the top 
      • Select 'Baselines' from the left

      sch_baselines_081622

      The 'Base Lines' screen shows the list of baselines with their details:

      • Baseline - The identification number of the baseline. The first approved schedule is saved as the primary baseline and is numbered as 'Baseline - 0.' The successive baselines are serially numbered.
      • Baseline dates - Start - The earliest start date set for a task in that baseline
      • Baseline dates - End - The most late end date set for a task in that baseline 
      • Baseline dates - Duration - The period between the earliest start date and most late end date set in that baseline.
      • Baseline dates - Variance Days - The schedule variance added by the effect of this baseline to the overall project schedule 
      • Project Progress - The current overall progress state of the project in percentage 
      • Status - Whether the baseline is saved as a draft or published. Only published baselines take effect on the master schedule

      Search and Filter options - Use the Find, Filter, and table customization options on the right to search, filter, add/remove columns, etc. See Search, Filter, Column Customization, and Table Views for guidance on this.

      Compare baselines

      The baseline comparison shows the side-by-side view of the selected baselines with lists of scheduled task items included in each. This enables you to assess the start/end dates and durations.

      • Open the 'Baselines' screen as explained above
      • Select the baselines you want to compare, a minimum of two
      • Click '+ Compare' at top right

      An example below shows a comparison of a baseline revision with the primary schedule (Baseline-0):

      The comparison shows the side-by-side view of the baselines. The list shows only the items revised by the selected baselines, with start/end dates and duration defined for each task as per the respective baseline. This allows you to compare the changes in the timelines of tasks present in the compared baselines. 


      Was this article helpful?