Update task progress
  • 1 Minute to read

    Update task progress


      Article Summary

      The foreman app lets you report the progress state of the tasks they oversee, for example, at the end of each day. The progress updates data are used in various modules, like the contractor schedule updates, daily reports, financial calculations, and more. Also, the task progress reports help the project managers to keep track of the field tasks and plan for upcoming tasks. 

      To update the progress of a task

      • Tap the 'Planned' or 'Pulled' tab
      • Tap a task under execution to open its task management screen

      The 'Task Completion' slider shows the current percentage of work completed so far.

      • Use the slider to update the current progress percentage

      A confirmation appears with a date selector:

      • Use the date picker and set the progress update date
      • Tap 'Update'

      The progress is recorded:

      • Repeat the process to update the progress at successive stages till the completion
      Tip:
      You can also attach photographs to indicate the state of the work while updating a task progress percentage. This is used in the daily field reports and other records. See Attach task progress photos for more details.