Add dependencies
  • 3 Minutes to read

    Add dependencies


      Article Summary

      Tasks are interdependent, such that the execution of certain tasks has to wait for the commencement or completion of another task or other tasks.

      Predecessors are the WBS/schedule elements that need to be compulsorily started or completed before you can start a certain task. You can specify the predecessor tasks and the dependency relationship in the 'Depends On' column for each dependent task. Also, you can add any delay or slack to be imposed before starting a dependent task. The start date of the dependent task is auto-calculated based on the predecessor task and the dependency relationship. But you can manually change the start date as required. You can edit or remove dependencies of a task any time. You can perform the following actions for all the tasks in your schedule,

      Add dependencies

      Edit dependencies

      Remove dependencies

      Note:
      If you update the start date of a dependent task, which is not in compliance with the type of dependency and lag days given to the predecessor task, you will receive an alert on the dependency violation.

      Task dependencies play a vital role in calculating the critical path in your schedule. The critical path indicates the essential tasks that must be compulsorily commenced and completed as per the planned dates without any delays in order to complete the project in a timely fashion.

      To add dependencies to a task

      • Navigate to the schedule page of the project
      • Ensure that you are in the grid view
      • Double-click inside the 'Depends On' column of the task row

      The 'Dependencies' dialog opens for the task:

      • Enter the details of the dependencies:

      WBS - Task Name - The predecessor task. 

      • Click inside the field to reveal the drop-down button
      • Click the down arrow and choose the task from the dropdown.

      Type - The dependency relationship. 

      • Click inside the field to reveal the drop-down button
      • Click the down arrow and choose the relationship

      The available options are:

      • SS - Start to Start - The successor or the dependent task can commence only after the predecessor task has started and is under execution.
      • FS - Finish to Start - The most common dependency relationship. The dependent task can commence only after the completion of the predecessor task. 
      • SF - Start to Finish - The dependent task can commence before the predecessor task but can be completed only after the commencement of the predecessor task.
      • FF - Finish to Finish - The tasks can be started independently, but the dependent task cannot complete until the predecessor task is completed. Both need not end up at the same time.
      • Lag Days - The time delay imposed between the predecessor and successor tasks, depending on the dependency relationship. You can specify the delay as the number of days or percentage of completion of the predecessor task.
        • Double-click inside the cell and enter the value
        • Enter the value as zero if you do not want to add any time lag

      Example - If you want a dependent task to start after three days from the commencement of the predecessor task, choose 'SS - Start to Start' as the relation, and enter 3 in the text box.

      • Click '+ Add' and repeat the process to add more predecessor tasks and dependency relationships.

      The dependencies are shown:

      • Click 'Save'

      The predecessor tasks and their dependency relationships are added to the task. You can view them in the 'Depends On' column of the 'Schedule' interface.

      You can add more dependencies at any time. But you cannot edit saved dependencies.

      To edit a dependency of a task

      • Navigate to the schedule page of the project
      • Ensure that you are in the list view
      • Double-click inside the 'Depends On' column of the task for which you want to edit the dependency

      All predecessor tasks and their dependency relationships are shown as a list:

      • Click inside the rows to edit the details of the dependencies
      • Click '+Add' to add more relationships
      • Click 'Save' for your changes to take effect

      To remove a dependency of a task

      • Navigate to the schedule page of the project
      • Ensure that you are in the list view
      • Double-click inside the 'Depends On' column of the task for which you want to edit the dependency

      All predecessor tasks and their dependency relationships are shown as a list:

      • Right-click on the row to edit or remove the details

      • Click 'Remove' to delete the dependency
      • Click 'Save' for your changes to take effect
      Note:
      You cannot edit or remove the dependencies of the task that are published or moved to the field.