Add an inspection event
  • 1 Minute to read

    Add an inspection event


      Article Summary

      The scheduler allows you to add inspection events to the schedule at any stage of work that requires site inspections and certifications by municipal and county authorities, site walk-throughs by the general contractor and the owner, periodical inspections by stakeholders, etc.

      To add an inspection

      • Navigate to the schedule page of the project
      • Identify the row containing the schedule item after which you want to insert an inspection event
      • Right-click on the row and choose 'Add Inspection' from the options

      A new inspection row gets added. The new row is indicated with the inspection icon:

      By default, the duration is set as one day and the date is set as the end date of the parent task.

      • Double-click inside the 'Task Name' cell and enter a label for the inspection event
      • Set the predecessor task for the inspection. The start date is automatically set as the next day to the end date of the predecessor task. See Add dependencies for more details.
      • Change the date for the inspection if required.